Cross River Rail (CRR)

Exactly. The total CRR cost being used by the Government now is not being disclosed in some great move for transparency, it was done purely to create the biggest dollar figure possible to completely erroneously compare to the previous Government’s stated CRR cost.

Great. So they have already been disclosed for and in a level of detail that allows them to be understood and scrutinised. Rather than some vague total cost with unclear scope and parameters.

So the car dealer is responsible for the running costs of the car over its lifetime? Where do you draw the line? Car cleaning? Tolls? It makes no sense.

No, they are telling you how much it will cost to purchase that product they are selling. Much like it works for all products and services…

When I purchase groceries should the supermarket tell me how much it will cost to cook it?

Or for new clothes, the cost of washing and maintaining them?

Costs are costs! Not zero!

Truly absurd…

10 Likes

Discounted cash flows (DCF) is a core finance principle, and is relevant for PPPs.

This is a PPP, not a traditional project. So we cannot ignore that future availability payments stream that the Queensland Government has promised to pay (“operational costs”).

Currently CRR is a mix of public and private financing. Suppose the private financing component of CRR were increased to 100%. Under the approach you’ve suggested @ClevelandLine tunnel would appear to have zero cost. I would suggest that’s the absurd result.

I have no idea how you’ve reached that conclusion from my post. You’re comparing different financing options.

6 Likes

Going back to a diagram that Ari posted earlier in this thread. Here you can see that the Auditor-General presents two sets of numbers through time:

  • A core project cost which starts off around $6.9b in 2017 and rises to $12.4b in 2025, and
  • A total cost which also starts at $6.9b in 2017, but then rises to $19b (prefaced by the words “… bringing the total overall CRR project cost to…”).


Source: QAO Audit Brief 17 December 2025.

The Auditor-General of Queensland is an independent agency. Even if we were to go with the QAO report’s lower figure of $12.4 billion, that is still a large 2x cost increase on Red Team’s $6.3 billion (year 2023) figure mentioned earlier in this thread.

The $19 billion figure in Ministerial Media Releases probably has a mix of various things that should or shouldn’t be there, but setting that to one side for a moment - the basic cost does seem to be at least $12.4b.

If we are to quote figures different from the independent QAO, then naturally, we’ll have to explain the variation between our figures and theirs. IMO from what I have read, the PPP availability payments over the 25 year duration should be incorporated because these are real cash outflows.

If there are still questions about what the QAO has published, then I would recommend contacting the QAO asking them for more information on how they arrived at their figures and what was included in them.

Independent Check
As an independent check, you could also perhaps use the Sydney Metro as a comparison. This has a construction cost of about ~ $1 billion/km. CRR is 10.2 km line, so you would expect the ballpark figure to land around $10.2 billion. This figure is in close agreement with the QAO core project figure of $12.4 billion.

In the next post, I’ll publish the output when I put this question to ChatGPT.

Notes
https://www.parliament.qld.gov.au/Work-of-the-Assembly/Tabled-Papers/docs/5825T2025/5825t2025.pdf

1 Like

The ChatGPT View: (Version 5.2)

Query
When assessing what the cost of the cross river rail project is, does it make sense to include or exclude the PPP availability payments that are to be paid over the 25 year period?

The interesting bit from the response:

  • Strict build-only costs do not represent full real-world costs or budget impacts
  • Recommendation to present both figures (which is essentially what the QAO has done).

ChatGPT Response:

Short answer: it depends on what question you’re trying to answer.
But for most policy and value-for-money discussions, you should include PPP availability payments (in present-value terms)—while for capital cost discussions, you usually exclude them.

Below is a clean way to think about it, using Cross River Rail as the example.


1. What are PPP availability payments?

Availability payments are:

  • Regular payments made by the public sector (here, the Queensland Government)
  • Over ~25–30 years
  • To the private consortium (e.g. PULSE)
  • In return for design, construction, financing, maintenance, and asset availability

They are not just “operating costs”—they embed:

  • Capital repayment
  • Financing costs
  • Lifecycle maintenance
  • Risk premiums
  • Private return on capital

2. When it does make sense to include availability payments

You should include them (discounted to NPV) when the question is:

:white_check_mark: “What is the true long-run cost to taxpayers?”

Because:

  • Availability payments are real cash outflows
  • They represent the price of procuring the asset via a PPP
  • Excluding them materially understates fiscal impact

This is the correct framing for:

  • Value-for-money analysis
  • Intergenerational equity
  • Comparisons with public-sector delivery
  • Budget sustainability discussions

In PPP economics, the Net Present Value (NPV) of availability payments is effectively the economic cost of the project.


3. When it does make sense to exclude availability payments

You can reasonably exclude them when the question is:

:warning: “What was the construction / capital cost?”

Here, people are usually referring to:

  • Tunnels
  • Stations
  • Rail systems
  • Civil works

In that case:

  • You quote the capital cost at completion
  • Availability payments are treated as a separate financing/operations stream

This framing is common in:

  • Engineering discussions
  • Media headlines
  • Comparisons with other projects’ build costs

But it is not a full economic cost.


4. The common mistake (and why debates get messy)

A frequent error is:

“Cross River Rail cost $X billion”
while excluding availability payments,
and then
“PPP is cheaper”

That comparison is invalid unless:

  • Availability payments are included or
  • A like-for-like public financing model (including debt servicing, maintenance, and risk) is also modelled

In other words:

  • Capital cost ≠ taxpayer cost
  • PPP cost ≠ construction cost

5. Best-practice answer (the one Treasury prefers)

The most defensible approach is to report both, clearly labelled:

Measure Include availability payments? Purpose
Capital / construction cost :cross_mark: No Engineering & delivery
NPV of PPP payments :white_check_mark: Yes Fiscal & economic impact
Whole-of-life cost :white_check_mark: Yes Value for money
Budget headline (cash) :white_check_mark: Yes Actual taxpayer outlays

Bottom line

  • Exclude availability payments → if you are strictly talking about build cost
  • Include (NPV of) availability payments → if you are talking about what the project really costs taxpayers

If you want, I can:

  • Walk through a worked example (PPP vs public delivery)
  • Help you frame a clear one-paragraph explanation for policy or public debate
  • Or show how this issue played out in other Australian mega-PPPs (Sydney Metro, WestConnex, etc.)

Regardless of the substance of the rest of the post, I wouldn’t call $2 billion, or a factor of 1.2, particularly close.

1 Like

If someone were to ask BTQ “What does BTQ think the real cost of Cross River Rail is?”, what would our number(s) be and why?

There seems to be a few options to choose from:

  • $6.3 billion (Red Team 2023 figure)
  • $8.018 billion (The budget that CRRDA has, including Private finance)
  • $12.4 billion (QAO core project cost, p25 of their audit brief report)
  • $19 billion (Blue Team’s figure)
  • Some other figure with certain things included or excluded

Would we be going with only say the strict build cost, or would we go for the full economic impact of the project as a whole, or something in between?

There is a $12.7 billion range between the lowest figure and the highest one, which is a bit of a gulf. :thinking:

What do members think the real figure is?

1 Like

My 2c, the Cross River Rail project now sits at $12.4 billion, including at least $2.6 billion in ongoing operations that did not form part of the original capital cost as well as $X billion in private financing, with the total program administered by the Cross River Rail Delivery Authority valued at approximately $19 billion.

2 Likes

I read through the QAO report the other day after it was posted and I think the brevity of it does come with some loss of clarity. It would be quite a task to try and cross reference the individual projects that are in CRRDA’s authority, particularly noting that the QTRIP is currently listing some projects as vaguely CRR additional works, and also listing projects that may or may not be core projects as delivered by CRRDA or delivered through a PPP arrangement. This is on top of Blue Team’s new approach to QTRIP of not actually assigning a budget amount publicly until after procurement is finalised.

2 Likes

It’s important to note how each of the different types of reports that the QAO produces are prepared. In this instance they state:

Data analysis
We analysed the publicly available data from the published capital budgets from 2021–22 to 2025–26 to form insights and make observations.

So the figures they are quoting are not independently financially audited. They’re compiled from what the CRRDA and Government publish.

I’m not saying QAO would accept them if they thought they were completely false but they aren’t audited figures.

I would suggest our response would be along the lines of:

A) We note the CRR figures have changed over the years showing an escalating costs but also recently including additional projects previously separately costed.

B) It isn’t possible for us to verify these. We call for full transparency on the breakdowns of the cost and reasons for changes in detail.

C) The main focus needs to be getting CRR complete and operational and maximising the value of it by sensible improvements to frequency across the network. However many billions the true cost is they mustn’t go to waste!

4 Likes

What’s your opinion on what the correct number is and why?

See above.

If anyone asked us, the answer I would want to give is ‘We don’t know, because the reporting has changed without enough transparency to be able to make a fair comparison’. We don’t have to know the answer to know the government is playing political games.

11 Likes

Like CRR don’t governments package in other projects for funding purposes. Similarly how Councils get away with not paying for sewage upgrades and streetscaping.

When they do this it seems to blow out the timeline of the project as they have added mini projects onto the main project. But as a funding model it’s quite smart.

I don’t see it as a political game, but more of a funding one.

It’s absolutely a political game because they are fudging the numbers to back up their claims of an ‘extreme cost blowout under Labor’. Politics at its worse. Yes, there have been incresses; no, it’s not as bad as they make it out to be.

13 Likes

I would agree with @mocon31. A $12.4 billion for the CRR project seems reasonable based on multiple approaches that give figures that cluster around this ballpark (see below). Note that the initial costing for CRR was around $5.4b.

Given that getting actual granular breakdowns of CRR figures might not be possible, a workaround is to look at comparable AU or NZ city rail tunnel projects and pull out an expected construction value for CRR.

Rough Estimations

Sydney Metro - $1 billion/km x 10.2 km = $10.2 billion
Auckland City Rail Link (CRL) = AUD $1.3 billion/km x 10.2 km = $13.26 billion
Melbourne Metro Tunnel = $1.49 billion/km x 10.2 km = $15.1 billion

Based on this method, a $5-$8b figure for CRR is likely to be a very substantial underestimate of the true cost of CRR. And the QAO core project cost figure of $12.4 billion is sitting within the range given by the comparable Sydney, Melbourne and Auckland rail tunnel projects.

All of these estimates and interpolations are coming far above a $5-$8b figure for CRR.

Conclusions

  • Does there exist a cost blowout? - Yes.

  • If there is a blowout, is it large? - Yes. It seems far above the initial project cost estimate of $5.4 billion.

  • Importantly, it is worth noting that all three reference projects in Sydney, Melbourne, and Auckland also suffered significant cost blowouts. This suggests that project management was only one of many factors that resulted in large cost escalations.

In the end, CRR is going to open a bit late and with higher costs, but the important thing is that it will be finished and we will have it.

Notes
Melbourne Metro Tunnel - $13.48 billion / 9 km = $1.49 billion/km unit cost
Auckland City Rail link (NZ) - $5.5 billion / 3.5 km = NZD $1.57 billion/km unit cost or around AUD $1.3 billion/km

Melbourne Metro Tunnel Costs

Auckland CityRail Link Tunnel Costs (NZ)

2 Likes

I’d probably caveat that I answered your question with what I think the number should be if pressed on it. The answers that @rowangray and @ClevelandLine gave are better in the first instance, because by now the point shouldn’t be the cost as much as the opaque way that both sides have been presenting, and ensuring that what we get is the best we can get.

4 Likes

If we’re talking about $12~13 billion for a very neutered project that will still require a lot of bad compromises across the entire network…

Yeah nah mate. Good luck trying to make this pass the pub test.

The southern portal is in the wrong place, the northern portal ends up at a station with bad connections (and then to another station that’s even worse!), and both sides of the new Sector 1 will still have major choke points in terms of level crossings, lack of fourth tracks, non-compliant platforms, etc, etc.

I hate to compare, but once you get to experience the Metro Tunnel in Melbourne you realise how well thought out (I do miss a station at South Yarra though) and easy to understand the new project is.

It genuinely hurts to see.

Sure, we’re getting a new tunnel… But one that solves very little.

3 Likes

I think people are really building a false narrative there.

1 Like