Cross River Rail (CRR)

Prices high probably due to workforce shortages and a lot of alternative projects going on up and down the east coast.

Queensland Government already has a public construction firm called QBuild.

QBuild doesn’t have the size or expertise to independently undertake a project of the scale of Cross River Rail. With the exception of smaller scale maintenance works, QBuild almost always undertakes projects together with private enterprise.

1 Like

If that’s the case, why weren’t they on the project

Because this isn’t the sort of thing that they do? In my understanding they barely do anywhere near as much actual construction at schools and public housing compared to what they did before Blue Team were around last time, with a lot more private sector companies used now.

1 Like

Looking at how existing projects are going suggests that future projects might have similar issues.

Cross River Rail has ongoing cost pressures and a revised delivery timeline

The Cross River Rail project continues to experience higher material and labour costs, workforce shortages, supply chain disruptions, and reduced productivity from industrial action. The project scope also includes associated works such as tunnel integration, train stabling facilities, signalling systems, and future operations and maintenance costs. Together, these factors have increased the overall project cost and extended the completion time frame. In 2024–25, the delivery authority renegotiated costs with its delivery partners for 2 major work packages, contributing to the project’s revised cost and schedule. In October 2025, the Queensland Government announced that the total project cost will now exceed $19 billion, with first passenger services expected in 2029.

(Bolding added)

Notes

Queensland Audit Office - Major projects 2025 Report 8: 2025–26
https://www.parliament.qld.gov.au/Work-of-the-Assembly/Tabled-Papers/docs/5825T2025/5825t2025.pdf

1 Like

This $19 billion seems to be high. Does anyone have a break up into the various items that give rise to this total?

1 Like

A ministerial statement from Dec 2024 breaks it down into:

  • $10.5B for construction + 25 years of maintenance
  • $5B for trains (QTMP?), stabling, signalling, rail replacements during construction, maintenance facilities, and “integration works” (presumably other projects)
  • $1.5B for “late running and contractor claims”

Last cost estimate from the red team before departure was $6.3B spend, and that’s for construction only.

The link Metro posted above (probably the most reliable of the bunch) isn’t entirely clear, but does include this chart


Looking further at pages 25 & 26, as far as I can tell

  • $8.3B + $1.5B private funding for ‘core project’ (which, assuming everything grew in cost evenly from 2019 roughly breaks down into:)
    • $6B for tunnels, stations, and development
    • $1B for rail, integration, and systems
    • $2.8B for land acquisition, contingencies, and other project costs
  • $3.6B for associated project costs, seemingly all funded by QR & TMR (again, assuming even cost growth breaks into:)
    • $1.8B for ETCS
    • $1.8B for rail, integration, and systems
  • $2.6B for 25 years of operations and maintenance
  • $3B for ‘associated project costs’, which include “tunnel integration with the existing rail network, train stabling facilities, signalling systems, temporary bus services during construction, and maintenance equipment”. We also know from the media release above that this includes the new QTMP trains

Some personal thoughts:

  • Red team estimate of $6.3B from 2023 lines up perfectly with the state contribution to the CRR project at that time. I think if we want to do any meaningful comparison our cost for CRR is now $8.3B
  • Blue team is counting the cost of the whole project including private funding and separate ETCS/RIS that QR is paying for, so that’s already a ‘blowout’ up to $13.4B without an additional cent being spent. I don’t think this is unreasonable per se (certainly the QR portion is also a state cost), but it’s odd to change costing half way through
  • Blue team has additionally added 25 years of maintenance and ops to the cost (which we already knew about), as well as factored into what seems to be the entirety of the QTMP project, rail replacement buses, stabling, and god knows what else. I don’t really have any way to describe this other than dodgy to the point of lying to the public. Really disappointing
  • I really doubt (with absolutely no qualification to do so) that ETCS & QR RIS has somehow blown out from $1.3B to $3.6B in 5 years. Especially given the announcements of more sections of the network being upgraded to ETCS, I suspect this is scope creep and that the $3.6B figure includes a lot more signalling upgrades that have been either added or moved from other projects
10 Likes

it is dodgy! no need to mince words here.

also

and reduced productivity from industrial action.

god forbid workers be safe in their workplace

1 Like

Thanks. Summary from the Audit Report.

1 Like

An alternative view is that this is the comprehensive cost. The Red Team figure is the cost for one component only. So it’s possible for both figures to be correct at the same time.

Total project cost = Capital cost + Operational costs + Financing costs

Red team have been citing only one component, which has been the traditional approach, but that doesn’t make it the right one.

And when you think about counting benefits, those benefits generally originate in the operations, not the capital works. The value comes from the existence of the service - reduced wait times, speed increase, reduced access times.

If one is going to include benefits from operations in BCR, then for consistency, then shouldn’t one also count any costs from operations too?

There is a very big difference in benefit from a new rail line that runs 1 train per hour to the exact same rail line that runs 4 trains per hour.

1 Like

I do think there’s an argument for some components such as the QR-bourne costs, but others like the 25-year maintenance & QTMP costs are pushing it too far IMO. New trains & stabling are hardly part of the tunnel or needed as per the QR statement at budget estimates, and tunnel maintenance, while definitely a cost, isn’t factored into any other infrastructure project I’ve heard of and is thus pretty misleading. I do think there’s merit in knowing the total cost of the CRR project, any complementary works (such as additional ETCS upgrades), new rollingstock, etc that we’d need to do a network-wide upgrade, but I’d also argue that’s such a different thing to the original cost that it’s misleading to pretend this is simply a budget blowout rather than an entirely different number.

4 Likes

I hear you. But there is a difference between the tunnel and the project. For example, new stations on the Gold Coast logically don’t have a connection with the CRR tunnel, but seem to have been marketed and packaged with it.

New trains and QTMP probably don’t have a strong connection, however if the gradient of the tunnel or the spacing of the doors matching the platform doors precluded the use of existing trains, then there well could be a case for including the QTMP trains in the project.

Traditionally, only the construction cost was quoted, but i’m not seeing a defensible case for doing that. Operations cost money too. If we count benefits arising from operations, then we should count costs from operations IMHO.

For example, if I were to buy a car, I wouldn’t only consider the purchase price as the total cost. I’d also consider the operating cost, maintenance, rego, etc over the life of the asset too.

We know for a fact that ALL trains have the same door spacing and the NGRs will be able to use the tunnel. I get playing devil’s advocate but this is being far too generous.

The defensible case is that this is how ALL projects in Australia are traditionally costed. Why change that now? Sure, you can make an argument that it shouldn’t be that way, but it makes NO sense to be so cagey about what makes up the figure UNLESS the reason is untoward.

Sure, you may consider it, but you don’t go into the dealership and see the TOTAL cost of the asset over its lifetime in bold on the vehicle.

4 Likes

Another question is, seeing as the QTMP will be required for the running of the line to Maroochydore due to the increased fleet requirements, why isn’t the QTMP being included in The Wave Stage 1 and 2 costs? Why isn’t Clapham Yard being included because it will hold the trains running on the line?

This is the reason why we don’t include these disparate projects in the costs. They are benefiting multiple separate projects and there is no sane or rational way to determine how you divvy up the cost. Are we going to start attributing 50% of the QTMP costs to CRR and 50% to The Wave to be fair?

5 Likes

The defensible case is that this is how ALL projects in Australia are traditionally costed.

Total Project Cost = Capital Cost + Operational Costs + Financing Costs

It makes sense to quote the Total Project Cost. Doing so won’t be misleading, provided that the three component costs - capital costs, operational costs, and financing costs are also quoted alongside.

Thinking about this, quoting only the construction cost is like buying a house and then failing to take into account the annual mortgage interest repayments, council rates and maintenance over the 25-year life of the home loan. These are all real cash outgoings.

It seems less transparent to only quote one and omit quoting the other two, even if based on ‘tradition’. Operations and maintenance cost money. One has to ask, what is the benefit of concealing / omitting those?

I’d recommend asking Translink or Queensland Treasury why the trains were included, and if they are operable outside of CRR and the GC/Beenleigh lines. This will settle the speculation.

  • In many English-speaking countries, the trend is specific train rollingstock for specific lines. The question we need to figure out is whether this applies to CRR.
  • If the QTMP rollingstock is specific for lines running in and out of CRR and cannot be used elsewhere on the network, then it probably should be included; if not, then it probably should be excluded.

Sure, you may consider it, but you don’t go into the dealership and see the TOTAL cost of the asset over its lifetime in bold on the vehicle.

Well, maybe they should start doing that. IMO it would be more honest and upfront, and people could make better more informed decisions.

Excerpt from RACQ website (annotations added)

We know it’s being designed for the existing QR loading guage. A possible ‘restriction’ to lines running through the tunnel are operational only.

3 Likes

You’re taking this too far. Of course they won’t do that because it depends on how it is used by the owner. You also don’t see the maintenance costs for a house on the sale price; and yes mortgage payments are different to maintenance costs.

5 Likes

Costs are costs, whether they are hidden, or variable, or difficult to estimate, or all of these.

It’s all going to come out of the bank account in the end.

If they are not zero, then they need to be disclosed.

I don’t disagree, but this pedantry is implicitly defending the current government for an obviously political decision to include these costs in the quoted figure without adequately disclosing it. You’d find the previous government did disclose these costs under different budget items which is completely fair, and actually far more transparent. We knew what each individual component costed. Now it’s far more opaque.

The upfront cost of construction is rarely included under the same budget item as the ongoing maintenance of the asset. The examples of a car and a house prove this. Sure, you should consider it, but there’s a reason it isn’t in the upfront price: because it is extremely dependent on individual factors which can not be foreseen. It’s also a very different life-stage of the asset. Why should it be included under the same budget item?

10 Likes

The upfront cost of construction is rarely included under the same budget item as the ongoing maintenance of the asset. The examples of a car and a house prove this. Sure, you should consider it, but there’s a reason it isn’t in the upfront price: because it is extremely dependent on individual factors which can not be foreseen. It’s also a very different life-stage of the asset. Why should it be included under the same budget item?

Cross River Rail is a PPP. The State of Queensland will pay “Project Co” (comprised of PULSE and others) tunnel availability payments (every quarter, in arrears) for 25 years to pay off the private consortia who are building and maintaining Cross River Rail.

The Pulse Consortium is comprised of CIMIC Group companies, Pacific Partnerships, CPB Contractors, and UGL with international partners DIF, BAM, and Ghella Investments & Partnerships.

Now, we can think about this stream of future availability payments as the operating cost of the CRR tunnel, from the Queensland Government perspective. Why? because it is drawing out cash from the State Budget for 25 years.

Excerpt - CRRDA Tunnel, Stations and Development Public Private Partnership Project Summary (p20, published March 2020)

The line “This net present cost represents the current cost of the future stream of net cash outlays…” means that the future costs over this 25 year period are foreseeable. At the time, this stream of payments was expected to sum up to around ~ $3.8b.

The cost is therefore not just the state-financed construction part of CRR (presumed to be Item 19 in the above image), but also the sum of these future availability payments to “Project Co”, adjusted to be in today’s dollars (Item 20). Annotations added.

Taking this information as a whole, IMO there is a good case for including maintenance/operations (e.g. the PPP availability payments to) as part of the cost of CRR. That is because (a) it is a PPP with availability payments the Queensland Government has promised to make, and (b) the stream of payments is reasonably certain.

Notes

The three major contracts, including the PPP, appear on the CRR Authority website:

Project Delivery

Cross River Rail is being delivered in partnership with the private sector through three major infrastructure packages of work: the Tunnel, Stations and Development (TSD) public-private partnership; the Rail, Integration and Systems (RIS) alliance; and the European Train Control System (ETCS) contract.

CRRDA Tunnel, Stations and Development Public Private Partnership Project Summary